As of 11:30 am Saturday, there are approximately 9,300 meters without power and over 25,800 meters that have been restored. We are on track to reach 90% restoration system-wide by 10:00 PM tonight.
Based on progress of work this morning and further repair work needed, we have the following estimated times of restoration.
Substations with services that should be restored to 95% by 10 pm Saturday, 9/28:
- Harbinwood
- Havana
- Hilliardville
- Hinson
- Killearn
- Lake Bradford
- Point Milligan
- Shadeville
- Woodville
Substations with services that should be restored to 95% by mid-day Sunday, 9/29:
- Baker
- Buck Lake
- Chaires
- Miccosukee
If your substation is not listed, it is already at or above 95% restoration.
We thank you all for your patience and continued support!