| Alerts
We understand how frustrating it can be to wait for your power to be restored, and we appreciate your patience. The restoration process is complex, and we want to assure you that a dedicated team of staff and lineworkers are actively working across our communities to restore power as quickly, safely, and efficiently as possible.
Talquin’s committed crews, alongside our mutual aid partners, are working around the clock. In just over 36 hours, we have assessed damage across our four-county, 2,600 square mile service territory and restored service to over 31,734 meters, achieving more than 90% restoration in our system. We are on track to meet the following estimated times of restoration:
✅ Substations with services that should be restored to 95% by 10:00PM Saturday, 9/28: Harbinwood and Shadeville.
✅ Substations with services that should be restored to 95% by mid-day Sunday, 9/29: Baker, Buck Lake, Chaires, Miccosukee.
🔔 If your substation is not listed, it is already at or above 95% restoration.
The next update will resume Sunday morning. To stay informed, please visit our outage map on our website: https://my.talquinelectric.com/outages/maps/
.