Our dedicated crews and mutual aid assistance that arrived yesterday are working to repair damage and restore power. We’re extremely grateful to have additional mutual aid crews joining the effort today.
Here are the estimated times for substations to reach 90% service:
- Hilliardville: Expected by 6 p.m. on the 11th
- Lake Talquin: Expected by 10 p.m. on the 12th
- Brickyard: Expected by 10 p.m. on the 12th
- Chaires: Expected by 10 p.m. on the 12th
- Woodville: Expected by 10 p.m. on the 12th
All other substations are already at 90% service. The remaining 10% of services across all substations may experience longer restoration times due power lines down and other situations.
Because there are still trees and power lines down, we urge everyone to exercise extreme caution if encountering these conditions.
Reporting Outages:
- Call (866) 899-4832 (Automated System)
- Call (888) 802-1832 (Live Operator)
- Text #OUTAGE to 85700
- Report via myTalquin app
Please visit our outage map for the most up to date information regarding outage numbers.
Thank you for your patience and cooperation as we work to get everyone’s power restored.